• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

University of Arkansas System

  • About
  • Campuses & Units
  • Leadership
  • System Office
  • Policies
  • News
  • Benefits
  • Campus Resources
You are here: Home / Campus Resources / Construction Contracting Procedures / Substantial Completion

Substantial Completion

  1. Unless defined otherwise in the contract documents, substantial completion is the stage in the progress of the work when the work or a designated portion thereof is sufficiently complete in accordance with the contract documents so that the owner can occupy or utilize the work for its intended use. If AIA 2017 documents are used, refer to A201-2017, Article 9.
  2. Upon substantial completion, follow the process prescribed in the contract documents. The contract documents may provide for a design professional (often an architect) to identify the time of substantial completion.
  3. The general contractor must notify all parties involved of the proposed date for substantial completion. The project architect or engineer will schedule and carry out the inspection to verify whether the construction is substantially complete.
  4. The contractor will notify the design professional that the project is ready for final inspection, at which time the design professional, with the campus, will conduct a final inspection.
  5. A punch list will be developed for all items that need to be corrected or completed.
  6. All major building systems, including mechanical, electrical and fire alarms, must be thoroughly tested prior to building occupancy.
  7. If applicable, a commissioning agent will conduct extensive functional performance testing to ensure all systems perform in accordance with design intent. Generally, there are two seasonal peak load times (winter and summer) and it is necessary to functionally test system under peak load conditions for each season during the warranty period.
  8. The commissioning agent should review the following : control system programming, equipment start-up procedures, review of TAB (testing, adjusting and balancing) reports, record drawings and operations and maintenance staff training.
  9. The certificate of substantial completion establishes the date of substantial completion, and must state the responsibilities of the owner and contractor for security, maintenance, heat, utilities, damage to work, insurance, and fix the time when the contractor must complete the listed items.
  10. Contractor warranties commence on the date of substantial completion unless another timeframe is stated in the certificate or the contract. After the architect approves the certificate, it should be approved and signed following the process prescribed in the contract documents.

Primary Sidebar

Campus Resources

  • Governor's Executive Order on COVID-19
  • Board of Trustees Approval Process
  • Contracting Authority Guide
  • Construction Contracting Procedures
    • Board Approval Requirements
    • Construction Project Approval Process
    • Contracting Process
    • Awarding Professional Contracts
    • Bidding a Capital Construction, Repair or Renovation Project
    • Awarding the Construction Contract
    • Contractor Qualifications
    • Payment Requests and Processing
    • Construction Inspection and Observation
    • Project Document Management
    • Substantial Completion
    • Acceptance and Final Payment
    • Dispute Resolution
    • Building Standards
    • Reports to the Board of Trustees
    • Energy Performance Contracting Approval Process
  • Bond Issuance Procedures
  • Real Estate Transactions
  • Academic Program Changes

Recent News

Drafts of Proposed Board Policy Amendments Release for Sept. 26 BOT Meeting

UA-EACC Chancellor Cline to Retire in July 2026

UA Trustees to Retreat Aug. 5-6 at Rockefeller Institute

Contact Us

University of Arkansas System
2404 North University Avenue
Little Rock, Arkansas 72207
(501) 686-2500
Staff Directory | Privacy Policy

Accessibility issues? Email: accessibility@uasys.edu

UA System Internal Audit Fraud Hotline: (866) 252-9838

Footer

Universities

  • University of Arkansas, Fayetteville
  • University of Arkansas for Medical Sciences
  • University of Arkansas at Little Rock
  • University of Arkansas at Monticello
  • University of Arkansas at Pine Bluff
  • University of Arkansas at Fort Smith
  • University of Arkansas Grantham

Two-Year Colleges

  • Phillips Community College of the University of Arkansas
  • University of Arkansas Community College at Hope-Texarkana
  • University of Arkansas Community College at Batesville
  • Cossatot Community College of the University of Arkansas
  • University of Arkansas Community College at Morrilton
  • University of Arkansas Community College at Rich Mountain
  • University of Arkansas Pulaski Technical College
  • University of Arkansas East Arkansas Community College

Other Units

  • Division of Agriculture
  • Arkansas Archeological Survey
  • Criminal Justice Institute
  • Arkansas School for Mathematics, Sciences and the Arts
  • Winthrop Rockefeller Institute
  • University of Arkansas Clinton School of Public Service

© 2025 · University of Arkansas System · All Rights Reserved